What you're asking for isn't directly possible in Project. The best suggestion I have for you is to create a summary task around tasks 1-3, assign the resource to that and remove the assignment from tasks 1-3. This will force the first three tasks to be leveled as a group.
You lose some power of Project when doing this however: reporting actuals and so forth on individual tasks will be made harder to do.