tags:

views:

11

answers:

0

Hi all,

I am working with MPXJ framework to generate an XML file with i import into project 2007. I have run in to allot of problems but i can't seem to find an answer to the following.

I have a fixed Work and duration on a task, but when i add a resource and import it in project i get an error message:

"The resource is assigned outside the original dates for task 2 in project. The duration of this fixed-duration task will change to accommodate the resource assignment".

Project then changes the work and or duration value. that is not what i want. i want the resource to use the 24 hours calendar but i can't seem to attach the project 2007 standard calendar, so i thought lets make my own 24 hours calendar and attach that to resource. now i can't seem to set the 0:00:00 to 0:00:00 time in a work day.

ProjectCalendar calendar = projectFile.addResourceCalendar();
calendar.setName("24 Hours");
calendar.setUniqueID(Count);
calendar.setWorkingDay(Day.MONDAY, true);
calendar.setWorkingDay(Day.TUESDAY, true);
calendar.setWorkingDay(Day.WEDNESDAY, true);
calendar.setWorkingDay(Day.TUESDAY, true);
calendar.setWorkingDay(Day.FRIDAY, true);

Resource resource = projectFile.addResource();
resource.setUniqueID(Count);
resource.setName("Painters");
resource.setResourceCalendar(calendar);

Any one know of a solution to one get the default 24 hour calendar set to the resource of make my own.