I have a MS Project file which I am using the Primary Interop Assemblies to parse. How can I determine the lineage of a task? I was relying on the WBS code, however the client has started to fiddle with this field and it no longer represents the hierarchy of the data.

Edit: By lineage I mean a way to identify where in the hierarchy the task exists. By default the WBS code mimics this perfectly.

I need this information to determine what is the parent for a task.

Example

  • A
  • B
    • B1
    • B2
    • B3
  • C

The Lineage for B3 would be 2.3 (If we counted by 1, like project)

+1  A: 

Try the Task object's OutlineNumber property and the PredecessorTasks collection.

HTM

Colby Africa

Colby Africa
OutlineNumber did it! Thanks