Hi,

I’m struggling to write what I want to do as I’m not at all familiar with Microsoft Project so I hope someone can grasp what I’m after, lol!

I am creating tasks from code and settings the predecessors; however I also need to "indent" (Alt+Shift+Right) rows so that there sub grouped (subtask) to the row/task above.

Any help much would go a long way, Many Thanks Dan.

+1  A: 

OutlineLevel :-)

Dan Bater