Hi,
In my excel I have the project status in hours only .
it means
M1 4 hrs
M2 6 hrs
M3 10 hrs
M4 3 hrs
I have to create a excel so that if I give a start date all the simillar dates needs to be calculated based on 8 hrs working time.
for example if my start date 09/01/2010 (this is the date entered by me)(mm/dd/yyyy)
Start Date End Date
M1 09/01/2010 09/01/2010 (4 hrs)
M2 09/01/2010 09/02/2010 (6 hrs so talking 2 hrs from 09/02/2010)
M3 09/02/2010 09/03/2010 (6 hrs from 9/2/2010 and 4 hrs from 9/3/2010)
M4 09/03/2010 09/03/2010 (3 hrs from 9/3/2010)
Please any one can give me a suggestion.
Thanks, Aswini Mahesh.