When I check in code to our Team Foundation Server, I some times (probably more often than I actually do...) should associate my check-in with a task or a bug I am working towards. When I mark a task or a check in, it sets the Check-in Action to Resolve. But almost always, I just want to have it as just Associate. The result is that I often end up marking a task as resolved by mistake. Is there a way to make Associate the default when I mark a task?
Resolving a bug or a task should be something I actively select. Like, this work item is related to my check-in AND it is now resolved. Not, this work item is related to my check-in, and btw, I still haven't fixed it completely yet...