I am about to join a new software team midway through a project. They are using ExtremePlanner to track their progress.
While they tracking tasks completed, they are not tracking how the estimated size of the project is changing over time. In the short time I have been monitoring the project this estimate has changed faster than the completion rate of the tasks. My gut feeling says that this is not just a blip but a problem that has been consistent throughout the project lifetime.
But how do I prove or disprove this?
I have not found the ExtremePlanner metrics useful for this. I have been exporting the data to MS Excel but the exported task and story info is missing important data like the creation date. Working around this is a bit of work. Is there a better way of doing this?
Alternately am I making too much of this? It has been argued by some of my prospective team mates that since no new features have been added that the scope has not changed and it is not a problem. However I argue that since new work within the features is continually being found the scope is changing and that this needs to be taken in to account when estimating the release date.