views:

57

answers:

3

How do you deal with a client who has different time estimates for the software product than yours?

I am going to describe a scenario that is not mine, but that captures broadly the same problem. I am working as a subcontractor to a large company that has a programming department. The software project we are working on is in an area that the department believe they have a handle on, but because their expertise and mine are very different we tend to get different results.

Example: At the start of the project I suggested one way of development which they rubbished as being unrealistically difficult and suggested integrating a different framework (one they are familiar with) with the programming language we are using (Python) to get more or less the same result.

  • Their estimate for this integration: less than a week (they haven't done the integration before).
  • My estimate for the integration: above two weeks.
  • Using my suggested way to get the result needed (including using matplotlib among other libraries used elsewhere within the project): 45 minutes. This is not an estimate, the bit was actually finished in 45 minutes.

Example: for the software to be integrated with their internal system, they needed to provide a web service for me to use. They provided a broken one, though it does work with their internal tool (doesn't work with .Net or Java mainstream packages among other options). They maintain that it is my fault that the integration has taken longer than the time estimated.

The problem is not that they don't know, the problem is that they have enough knowledge about programming to be dangerous (in my opinion). Is there some guidelines for how to deal with this type of situation? A way for expectation management? Or may be I shouldn't get involved in such projects from the start and in this case what are the telltale signs?

+6  A: 

If a client isn't happy with a time estimate, don't do the work. If they think they can do it better or faster, tell them to go ahead.

The one thing I never allow is for my estimates to be modified. That's something that caught me out early on in my career but we learn our lessons.

If clients were so good at doing the work, they wouldn't be hiring me. I'd simply point out that they hired me for my expertise so why are they disregarding that expertise. Of course, if they were to allow the scope of the project to change (i.e., less work), that would be another matter, and one up for discussion.

If you didn't lock in exactly what they were meant to provide as part of the deal, then it's a "he says, she says" situation and, unfortunately, the customer controls the purse strings. However, often, the greatest power you can have is the ability to just walk away.

No-one says you have to do the job.


Of course, all that advice above is worth every cent you paid for it :-)

I don't know your specific circumstances.

paxdiablo
+1, totally agreeing there.
jv42
Thanks. Very good points. The advice is certainly worth way more than what I have paid:) (though I understand the disclaimer)
Muhammad Alkarouri
+1  A: 

Or may be I shouldn't get involved in such projects from the start and in this case what are the telltale signs?

My answer for sure. If you can avoid those projects, do it.

Some signs : people thinking they know how to do things when you can guess they can't. The "oh no let's not use this perfectly suitable tool because I don't know it" is a major indicator that the person is technically challenged.

jv42
+1  A: 

first of all, it is no fun to be in such an environment. So, if you like to have fun at your job, and you do not need to take this job for extenuating financial reasons, then simply do not take the job that is not fun.

Since that is hardly realistic in many cases, you will end up with the job and need to manage the situation as best you can. One way is to make sure there is a paper trail documenting your objections and concerns with the plan. Try not to be overtly negative, but try to be constructive and present valid alternatives. Here you will need to feel out the political landscape, determine if the 'boss' will be appreciative or threatened by your commentary, and act accordingly.

Many times there are other issues that management is dealing with that you are not aware of. Be cautious of this fact, and maybe ask the management team if this is the case, again without being condescending or negative.

Finally, if you have alternatives that take less time than the meetings it would take to discuss them, just try it in a sandbox, and show it off. This would go a long way to 'proving' your points. Caution here is that you could be accused of not being a team player, or of wasting resources, or not following direction. Make sure this is mitigated by doing these types of things on your own time, or after careful consideration of how long you are spending on these things as well as how vested your boss seems to be on the alternatives.

hth

Randy
"make sure there is a paper trail documenting your objections and concerns with the plan". Good point.
Muhammad Alkarouri