views:

460

answers:

4

In one discussion among colleagues I have heard that function point analysis is not used nowadays since it can go wrong for various reasons.

So WBS (work breakdown structure) is used commonly.

Is that true?

+1  A: 

I just took the introductory course of a project management program, and we didn't even look at "function point analysis" (I'm not sure what that is), but we spent a lot of time looking at WBS. All the following processes referred back to the WBS.

Robert Gowland
+6  A: 

Function Points and WBS are two different, but related items. Function Points is a unit of measurement that can be used to determine complexity and work effort, WBS (work breakdown structure) is an approach to define sub units to a project (problem).

SO, when starting a project with a given scope and set of expectations, you use a WBS to define the sub units of the project (to a degree that is useful for you), once you have well defined sub units, you can determine the work effort by assigning function points to each and multiplying velocity (# of function points per day that can be delivered- as an example).

Here are some useful links:

meade
+1 for good explanations of the involved theories-1 for not answering the question
Steen
A: 

I can only talk about what I have seen. I have seen IBM use Function Points in Mexico to determine product size and pay subcontractors.

Regards...

Kwang Mark Eleven
A: 

I did function point analysis back in university in the early nineties, but it never came up again once I actually entered the work force.

sean riley

related questions